Water System Upgrades

Water Bond Improvement Project List:


  

PROJECT UPDATES (week of 6-26-17):

 
    Jackson & Boys Ranch Water Supply Wells Rehabilitation Project: Production wells are drilled.  Bids opened on April 20, 2017 at 2:30 pm to connect newly drilled wells to the City's water distribution system. Contract awarded to Conco-West for $1.28M.  Construction to begin in June 2017. Plan sheets 1-5, plan sheets 6-10, plan sheets 11-15, plan sheets 16-20 , plan sheets 21-25, plan sheets 26-30 and plan sheets 31-34
    New Main Avenue Well Project: Design 100% complete. Preparing bid package. Bidding expected in June 2017 with construction starting in July 2017. 
    Oak Canyon Booster Station Project: 95% complete. New booster station building energized. Start-up in process. New Station should be online next week. The generator will be operating more frequently during this time.  Project Photos , plans.
     East Dunne Avenue Water Reservoir Project: Design 85% complete. Environmental studies almost complete.
     East Dunne Avenue Booster Station Project: Design 70% complete.
 